Stabilising Punta beach in Roses without moving sand after every storm
Stabilisation scheme for Punta beach, between the Ginjolers stream groynes and Roses marina, for Roses Town Council and its company Port de Roses.

The challenge
Since 1992 the beach has been rotating: waves drive the sand from north to south and it never reaches equilibrium. After every easterly storm it had to be pushed back by machine, an endless cost the port concession had to bear.
The solution
Based on an options study and bionomic mapping updated in 2025, we designed the partial submersion of the eastern breakwater of the Ginjolers stream, a new 80 m T-shaped groyne with its crest at level 0.00, and a reshaped beach plan using dredged sand between the two existing groynes. The new groyne sits where there is no posidonia meadow.
The outcome
A beach heading towards stable equilibrium, a cleaner bay landscape with the eastern groyne lowered, and a consolidated design that meets every authority’s conditions so it can go to tender.
- Project
- Stabilisation of Punta beach
- Client
- Ajuntament de Roses
- Location
- Roses (Girona)
- Year
- 2025
- Service
- Consolidated detailed design
- Sector
- Maritime
- Key technical aspects
- Coastal processesBreakwaters and groynesBionomic mappingMarine strategy
What you don’t see
The groyne sits flush with the water.
It slows sand transport without raising a visible barrier in the bay.