Stabilising Punta beach in Roses without moving sand after every storm

Stabilisation scheme for Punta beach, between the Ginjolers stream groynes and Roses marina, for Roses Town Council and its company Port de Roses.

Stabilising Punta beach in Roses without moving sand after every storm
80 m
of new groyne
+0.00
crest level
Since 1992
with the beach rotating
Posidonia
protected meadow avoided

The challenge

Since 1992 the beach has been rotating: waves drive the sand from north to south and it never reaches equilibrium. After every easterly storm it had to be pushed back by machine, an endless cost the port concession had to bear.

The solution

Based on an options study and bionomic mapping updated in 2025, we designed the partial submersion of the eastern breakwater of the Ginjolers stream, a new 80 m T-shaped groyne with its crest at level 0.00, and a reshaped beach plan using dredged sand between the two existing groynes. The new groyne sits where there is no posidonia meadow.

The outcome

A beach heading towards stable equilibrium, a cleaner bay landscape with the eastern groyne lowered, and a consolidated design that meets every authority’s conditions so it can go to tender.

Project
Stabilisation of Punta beach
Client
Ajuntament de Roses
Location
Roses (Girona)
Year
2025
Service
Consolidated detailed design
Sector
Maritime
Key technical aspects
Coastal processesBreakwaters and groynesBionomic mappingMarine strategy

What you don’t see

The groyne sits flush with the water.

It slows sand transport without raising a visible barrier in the bay.

More Maritime projects

See the sector →
Maritime2026 · Ports de la Generalitat

Dredging of the Vilanova i la Geltrú harbour entrance

Maritime2026 · Port Authority of Pasaia

Strengthening of the Buenavista quay

Maritime2021 · Club Nàutic Estartit

New concession for L’Estartit marina