WaterFontanelles, Muntanyola (Barcelona) · 2024

Ending untreated wastewater discharges in Fontanelles

Options appraisal and detailed design of the sewerage and treatment plant for Fontanelles, in Muntanyola (Osona). Lot 1 of the Consell Comarcal d’Osona tender, awarded to Enigest in 2024.

Ending untreated wastewater discharges in Fontanelles
350
population equivalent
901 m
of gravity sewer
26
manholes
0
pumping stations on the network

The challenge

Fontanelles had no wastewater treatment: sewage reached two streams. It is a second-home neighbourhood that grows from about 224 residents to over 330 in season, with planning capacity for 660.

The solution

We measure before we size: a sampling campaign in July 2024, on weekdays and holidays. We compared three technologies and chose rotating biological contactors, the most robust to changes in temperature and flow. The 901 m sewer runs by gravity under the street, with no pumping at all.

The outcome

A treatment plant for 350 population equivalent, with the site ready to grow to 700, effluent BOD5 < 25 mg/l, SS < 35 mg/l y DQO < 125 mg/l, canal de biorremediación y placas fotovoltaicas.

Project
Fontanelles sewerage and WWTP
Client
Consell Comarcal d'Osona
Location
Fontanelles, Muntanyola (Barcelona)
Year
2024
Service
Detailed design
Sector
Water
Key technical aspects
Rotating biological contactorsSampling campaignGravity networksSolar energy

What you don’t see

Before drawing a single pipe we surveyed 1,200 m of street and the 16 existing manholes, and sampled for two weeks.

The design starts from what actually flows through the network.

More Water projects

See the sector →
Water2025 · Aigües Ter Llobregat (ATL)

Connecting La Llagosta to the Ter-Llobregat network

Water2026 · EMACSA

Storm tanks in Córdoba

Water2026 · Agència Catalana de l’Aigua

Bot sewerage and WWTP