IndustrialCastelló d’Empúries (Girona) · 2025

Two plants against drought for the northern Costa Brava’s water

Detailed design and site supervision of an ultrafiltration plant and a reverse osmosis plant in Empuriabrava, for the Consorci d’Aigües Costa Brava Girona, at the height of the 2023–2024 drought.

Two plants against drought for the northern Costa Brava’s water
315 m³/h
of ultrafiltered water
180 m³/h
of RO permeate
90 %
RO recovery
14 %
reservoir level at Darnius-Boadella

The challenge

The Darnius-Boadella reservoir fell to 14 %, and the Empuriabrava drinking water plant, which supplies Roses, Castelló d’Empúries, Llançà, El Port de la Selva and La Selva de Mar, was receiving water from the Muga with ever more organic matter. More water, of better quality, was needed — fast.

The solution

Two containerised plants on concrete slabs. The four-container ultrafiltration plant, with a 350 m³/h inflow, cleans the water before it reaches the drinking water treatment plant. The reverse osmosis plant is fed by five new wells in the Parc del Trabuc and produces 180 m³/h at 90 % recovery.

The outcome

The ultrafiltration plant was built between June 2024 and February 2025, and the reverse osmosis plant between February and March 2025. More water, of better quality, for the northern Costa Brava.

Project
Ultrafiltration and reverse osmosis in Empuriabrava
Client
Consorci d’Aigües Costa Brava Girona
Location
Castelló d’Empúries (Girona)
Year
2025
Service
Detailed design and site supervision
Sector
Industrial
Key technical aspects
UltrafiltrationReverse osmosisContainerised plantsSite supervision

What you don’t see

Everything is housed in shipping containers: that is why the reverse osmosis plant went from setting-out to completion in under two months.

More Industrial projects

See the sector →
Industrial2024 · Private client

Extension of a paper mill pulp line in Mexico

Industrial2023 · Fundació Fira de Lleida

Hall 5 at Fira de Lleida

Industrial2026 · Barcelona Metropolitan Area (AMB)

Green roof renewal at Ecoparc 3