Replacing a bridge deck in Empuriabrava before it failed
Empuriabrava is the world’s largest residential marina, with more than 25 km of navigable canals. Over the main canal, the Barkitos bridge carries the traffic of Avinguda de la República Catalana.

The challenge
The prestressed beams had cracks, spalling and exposed, corroded tendons. In prestressing steel, corrosion advances very fast and makes collapse hard to predict: the condition report gave two or three years’ margin.
The solution
We ruled out repair. We designed a new deck of precast post-tensioned U-beams, spanning 5, 12 and 5 m, continuously post-tensioned end to end, on the existing abutments and piers, repaired and raised. We lifted the road level by 70 cm with 5.5 % ramps, brought footways and carriageway to the same level, widened the footways by a metre and separated pedestrians from traffic with an urban parapet.
The outcome
A new bridge, about 63 cm higher above the water, allowing more and larger boats through. The asbestos-cement pipes are replaced with stainless steel.
- Project
- New deck for the Barkitos bridge
- Client
- Ajuntament de Castelló d'Empúries
- Location
- Empuriabrava, Castelló d'Empúries (Girona)
- Year
- 2024
- Service
- Detailed design
- Sector
- Transport & Cities
- Key technical aspects
- Post-tensioned concreteStructural assessmentSite servicesAccessibility
What you don’t see
No service is cut off during construction.
The medium-voltage line goes overhead, gas and telecoms hang from the piers, and pedestrians cross the canal on temporary floating pontoons.