Transport & CitiesLa Pobla de Segur (Lleida) · 2025

Linking the two banks of the Flamisell with 78 metres of precast footbridge

A footbridge between Passeig 1 d’Octubre and Parc dels Raiers in La Pobla de Segur, a few metres from where the Flamisell meets the Noguera Pallaresa.

Linking the two banks of the Flamisell with 78 metres of precast footbridge
78 m
of deck
4
post-tensioned double-tee beams
500 years
design return period
3 months
construction period

The challenge

Linking two riverbanks for pedestrians with a structure able to withstand the floods of a mountain river and fit into protected undevelopable land.

The solution

A 78 m deck made of four precast post-tensioned double-tee beams, 3 m wide: two of 22 m and two of 17 m. We chose those lengths so the beams could travel by road from the precast yard without abnormal loads. They sit on abutments and piers founded to resist scour.

The outcome

A complete detailed design, with hydraulic, geotechnical, archaeological, environmental and landscape studies, designed to be erected in three months with minimal work in the river channel.

Project
Footbridge over the River Flamisell
Client
Ajuntament de la Pobla de Segur
Location
La Pobla de Segur (Lleida)
Year
2025
Service
Detailed design
Sector
Transport & Cities
Key technical aspects
Post-tensioned concretePrefabricationRiver hydraulicsLandscape integration

What you don’t see

The deck soffit sits at level 509.82 m.

It sits half a metre above the 500-year flood level, the freeboard recommended by the Catalan Water Agency.

More Transport & Cities projects

See the sector →
Transport & Cities2024 · Ajuntament de Castelló d'Empúries

New deck for the Barkitos bridge

Transport & Cities2026 · Viladecans Mediterrània (VIMED)

Can Sellarès development

Transport & Cities2026 · Vitoria-Gasteiz City Council

Armentia timber footbridge