Gauging the Brugent again, thirty years on
Design and site supervision of the new EA058 gauging station on the River Brugent at La Riba, for the Catalan Water Agency. Part of the high-availability monitoring network, also designed for early flood warning.

The challenge
The Brugent comes down from the Prades mountains on 3 to 4 % gradients, carrying gravel and boulders between unstable banks. It had not been gauged since 1994, and its flow needed to be known before it joins the Francolí.
The solution
We compared three sites on hydraulic, environmental and construction criteria and chose the old TV-7044 bridge. A drop weir that doesn’t trap sediment, a low-flow channel, a radar level sensor on the bridge and a capacitive back-up sensor in case the water rises above the soffit. Construction is carried out in two phases, always in the dry.
The outcome
The river is back on the gauging network, from low flow to flood, with its banks restored and free of invasive giant reed.
- Project
- Brugent river gauging station
- Client
- Agència Catalana de l’Aigua
- Location
- La Riba (Tarragona)
- Year
- 2026
- Service
- Detailed design and site supervision
- Sector
- Environment
- Key technical aspects
- HydrometryHydraulic modellingDrone surveyingSite supervision