EnvironmentLa Riba (Tarragona) · 2026

Gauging the Brugent again, thirty years on

Design and site supervision of the new EA058 gauging station on the River Brugent at La Riba, for the Catalan Water Agency. Part of the high-availability monitoring network, also designed for early flood warning.

Gauging the Brugent again, thirty years on
1994
last reading from the old station
67.5 M
drone survey points
69 m³/s
maximum recorded daily flow
3
sites analysed

The challenge

The Brugent comes down from the Prades mountains on 3 to 4 % gradients, carrying gravel and boulders between unstable banks. It had not been gauged since 1994, and its flow needed to be known before it joins the Francolí.

The solution

We compared three sites on hydraulic, environmental and construction criteria and chose the old TV-7044 bridge. A drop weir that doesn’t trap sediment, a low-flow channel, a radar level sensor on the bridge and a capacitive back-up sensor in case the water rises above the soffit. Construction is carried out in two phases, always in the dry.

The outcome

The river is back on the gauging network, from low flow to flood, with its banks restored and free of invasive giant reed.

Project
Brugent river gauging station
Client
Agència Catalana de l’Aigua
Location
La Riba (Tarragona)
Year
2026
Service
Detailed design and site supervision
Sector
Environment
Key technical aspects
HydrometryHydraulic modellingDrone surveyingSite supervision

What you don’t see

Below the low-flow channel we left a 40 cm pool so fish can move upstream: measuring a river shouldn’t cut it off.

More Environment projects

See the sector →
Environment2024 · Ajuntament de Santa Eulàlia de Ronçana

Flood protection on the River Tenes

Environment2026 · Barcelona Metropolitan Area (AMB)

Channel and lagoons at the mouth of the Besòs

Environment2026 · Agència Catalana de l’Aigua

Channelling of the Trinitat and Sant Salvador streams at Montserrat